Confidential Client


Itasca, Illinois

Next Generation Data Center Deployment

Project Details


  • Project Name:New 36MW Data Center
  • Project Type:Mission Critical | Data Center
  • Location:Itasca, IL
  • Contractor:Clune Construction Company
  • Architect:HED - Boston, MA
  • Engineer:HED - Boston, MA
  • Project Manager:Tim Riordan
  • Trades:Mechanical Piping & Sheet Metal
  • Completion Date:March 2023

The overall project consists of [2] 36MW Data Centers. The current project (Phase 1 of 2) is the first data center that is scheduled to be completed with a 100% build out of 6 data vaults by March, 31 2023. The second (Phase 2) is a 36 MW data center that will be similar to phase 1 and is scheduled to start at the beginning of 2023.

Phase 1 data center has [6] 6MW high density data vaults. There are [36] 350 ton each air cooled chillers. The data vaults have chilled water fan walls for cooling. The chilled water pumps are internal to each chiller. The building is two stories.