An all-star team of LU 597 fitters led by Bill Schaafsma and Tim Dircks, Jr. brought sixteen chilled water coils and six 1000 ton chiller bundles up the elevator shaft to the mechanical room on the 16th floor. We worked round the clock starting Friday night so it would be business as usual for the tenants come Monday morning. Now the race is on to have the complete new chiller plant up and running for the cooling season! Special shout out to Randy Byerley, Piedmont Realty, Leopardo, Otis Elevator and building personnel for all their contributions to a challenging yet ultimately successful operation!