Confectionary Plant


Project Details


  • Project Name: Confectionery Plant | HVAC Upgrade
  • Location: Chicagoland
  • Completion Date: May 2022
  • Architect: N/A
  • Engineer: GHAFARI
  • Contractor: AMS Industries, Inc.
  • Project Manager: Mike Catanzaro / Dave Dobson
  • Project Type: Mechanical Equipment Infrastructure Upgrade (Process facility).
  • Trades: Ductwork, Piping, Plumbing, Electrical, Structural, Fire Protection, Temperature Controls, General trades, and Mechanical demolition.

Project Description


The overall project consists of [2] 36MW Data Centers. The current project (Phase 1 of 2) is the first data center that is scheduled to be completed with a 100% build out of 6 data vaults by March, 31 2023. The second (Phase 2) is a 36 MW data center that will be similar to phase 1 and is scheduled to start at the beginning of 2023.

Phase 1 data center has [6] 6MW high density data vaults. There are [36] 350 ton each air cooled chillers. The data vaults have chilled water fan walls for cooling. The chilled water pumps are internal to each chiller. The building is two stories.

Project Photos


previous arrowprevious arrow
3